I.  INTRODUCTION

The City of Mesa (“Mesa”) invites your company (“Supplier”) to participate in submitting proposals to provide Mesa’s Electric Utility with electric power and energy to the delivery points specified in this Request for Proposals (RFP) to the terms described below.


II. ENABLING AGREEMENTS

Suppliers that want to sell energy to Mesa (but may not be able to deliver the products included in this RFP) may convey their interest in entering into Enabling Agreements with Mesa in writing (using the attached submittal page or a letter stating such intentions on company letterhead). Suppliers should also supply as much information from Section IV of this RFP as possible to assist Mesa in evaluating the Supplier's reliability and experience. Enabling Agreements are not guaranteed to be implemented as a result of submitting this interest.


III. REQUESTED BASE, SUMMER PEAK, JULY-AUGUST PEAK, AND SUMMER OPTION RESOURCE SUPPLY                        

Mesa is requesting proposals on electric energy supply products as specified below. Bidders may bid on any or all terms (Supply Periods) for any of the products. Each product will be selected independently of the others.  Mesa expects to transact on one term for each product:

Base Product

A base product (7x24 Firm Energy) covering all or any of the Supply Periods described in Table A-1 facilitated by use of WSPP Schedule C or EEI Firm LD.

 

Table A-1) Base Product

Supply

Supply Period Start Date

Supply Period Ending Date

Supply Product Description

Supply Quantity

Supply Months

Delivery Points Requested

Supply A

2/1/2022

12/31/2023

7x24 Firm Energy Product

10 MW

January - December

Mead 230 kV

West Wing 500 kV or Pinnacle Peak 230 kV

Supply B

2/1/2022

12/31/2024

Supply C

2/1/2022

12/31/2025

Mesa envisions executing only one of the supplies in Table A-1 if a supply agreement is executed.

 

Summer Peak Product: 

A Summer Peak product (7x16 Firm Energy) covering all or any of the Supply Periods described in Table A-2. Interested Bidders should submit Summer Peak Product proposals in the form of one of the following that covers all or any of the Supply Periods described in Table A-2 facilitated by use of WSPP Schedule C or EEI Firm LD:

Table A-2) Summer Peak Product

Supply

Supply Period Start Date

Supply Period Ending Date

Supply Product  Description

Supply Quantity

Supply Months

Delivery Points Requested

Supply D

6/1/2022

9/30/2022

7x16 Firm Energy Product

25 MW

June - September

Mead 230 kV

Supply E

6/1/2022

9/30/2023

Supply F

6/1/2022

9/30/2024

Supply G

6/1/2022

9/30/2025

Mesa envisions executing only one of the supplies in Table A-2 if a supply agreement is executed.

July-August Peak Product:

Interested Bidders should provide July-August Peak Product proposals in the form of one of the following that covers all or any of the Supply Periods described in Table A-3 facilitated by use of WSPP Schedule C or EEI Firm LD:

Table A-3) July-August Peak Product

Supply

Supply Period Start Date

Supply Period Ending Date

Supply Product Description

Supply Quantity

Supply Months

Delivery Points Requested

Supply H

7/1/2022

8/31/2023

7x16 or 6x16 Firm Energy Product

10 MW

July - August

Pinnacle Peak  230 kV

Supply I

7/1/2022

8/31/2024

Supply J

7/1/2022

8/31/2025

Additional Details:

All products must be delivered under WSPP Schedule C or EEI Firm LD terms to the locations identified in the Supply Periods Tables (Tables A-1, A-2 and A-3).  

As part of their response, Suppliers have the option to describe the source of the product they are providing (traditional generation facilities and/or generation facilities utilizing renewable resources such as solar, biomass, geothermal, wind power) and/or energy storage devices as applicable.

If the Supplier is expecting and can attest that a certain percentage of the energy will be from renewable energy sources, please indicate as such in your response.

Mesa is requesting pricing for a 100% carbon free scenario which can be supported through bundled RECs, unbundled RECs, carbon offsets, and/or specific carbon-free generating facilities.

Mesa is seeking physical, delivered energy and NOT a financial hedge or other derivative. 

Depending on the offers received pursuant to this RFP, Mesa may issue a request for best and final offers to specific firms. 

Should best and final offers be requested, Mesa will provide additional specifications to be addressed in the response from the selected firms.